Centurion has completed the construction of a new Interventional Radiology Wing at Geisinger’s Lewistown Hospital Location. The project was complex and fast-paced with little room for storage or logistics. It involved a 3,000 SF addition, work in Pre/Post Op Bays, Sterile Processing and the Boiler Room. Challenges of note for the project are:
- Engineering and Construction of a Temporary Bridge to Access the Site
- Deep Foundations within an existing Courtyard
- Structural Steel with ability to expand to a 2nd Story
- 11,000# AHU to serve the new Operating Room
- New Reverse Osmosis Water System to serve Sterile Processing Expansion
- New Utilities and Operating Equipment for Hybrid Operating Room